Project Details
Client
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.
Area of Expertise
Share Project
Description
The bridge and culvert condition data is to be collected twice a year during the pre-monsoon period and post-monsoon period for three years, with the help of the Mobile Bridge Inspection Unit.
The bridge and culvert inventory data is to be collected during the first six months of the contract period, using the data collection Tablet, using the Mobile Bridge Inspection Unit, and it needs to be updated every year.
All the bridge and culvert inventory and condition data is collected from the entire National Highway network, including the portion entrusted to NHAI or as per the direction of the employer.
In addition, all Bridges, Culverts, ROBs, and elevated structures are to be inspected using the MBIU.
Here are the details of the inspection:
Part A – Gujrat
Project Completed on – 25.10.2018
Sr. no. | Particulars | Number of Bridges |
---|---|---|
1 | Extra Long Bridges of Length greater than 150m | 174 |
2 | Major Bridges of Length greater than 60m and up to 150m | 387 |
3 | Minor Bridges of Length greater than 6m and up to 60m | 2949 |
Total No of Bridges | 3510 | |
Total no of culvert up to 6m | 5090 KM |
Part B – Maharashtra
Project Completed on – 02.11.2019
Sr. no. | Particulars | Number of Bridges |
---|---|---|
1 | Extra Long Bridges of Length greater than 150m | 157 |
2 | Major Bridges of Length greater than 60m and up to 150m | 346 |
3 | Minor Bridges of Length greater than 6m and up to 60m | 3298 |
Total No of Bridges | 3803 | |
Total no of culvert up to 6m | 12326 |
All the data was collected by digital inventory using advanced technology and software provided by the ministry. The MBIU machine has been used for a structural audit of the major structures.
Related Projects
Advanced Materials Used in Road Construction
With rapid urbanization and global industrial growth, traditional construction materials are becoming increasingly
The Psychology Behind Resistance to Change in Infrastructure Development
Infrastructure professionals often resist adopting new methods or technologies due to psychological barriers:
Expanding Horizons at ICTA 2024: Dhruv Consultancy
A Step Towards Global Expansion Dhruv Consultancy’s recent participation in the ICTA 2024